How your project budget is calculated

The difference between a base budget and a total budget, how Simple and Detailed modes differ, and what approved change orders and payments change.

A renovation project has two budget numbers. The base budget is what you plan and type in. The total budget is the base plus every approved change order. You edit the base. Re:InvestorHub works out the total for you.

On screen What it means
Total Project Budget (Simple mode) The base budget you type. It is the only budget field you edit in Simple mode.
Estimated Budget (Detailed mode) The sum of every line item’s Total. This is your base in Detailed mode.
Base Budget Shown at the top of the Budget tab once a change order has been approved. The base before change orders.
+ $X approved change orders The sum of the change orders you approved.
Total Budget Base plus approved change orders. The same figure appears in the Total Budget card at the top of the project.
Amount Paid The payments you have logged.
Amount Owed (Simple) / Remaining (Detailed) What is left to pay.

The Budget tab has a Simple and a Detailed switch. Switching does not delete what you entered in the other mode.

Simple is one number. You enter a Total Project Budget, then log payments against it. Amount Owed is the total budget minus Amount Paid, never below zero, and the progress bar shows paid as a share of the total budget.

Detailed is a budget built from phases and line items. A line item’s Total is its Labor plus its Materials, added for you. The base budget is the sum of all line item totals, and Amount Paid is the sum of the payments logged on the line items. Line items you have not placed in a phase are still counted.

  1. You edit the base. Type a new Total Project Budget in Simple mode, or add and change line items in Detailed mode. The total updates to match.
  2. You log a payment. Amount Paid goes up and Amount Owed or Remaining goes down. In Simple mode Log Payment is disabled until the total budget is above zero.
  3. A change order is approved. Its amount is added to the total budget in both modes. You do not edit the budget by hand. A change order that is still Pending or was Rejected adds nothing.

Only an Admin can approve a change order, so see How roles and permissions work if the Approve option is missing for you.

Maya budgets a rehab in Simple mode with a Total Project Budget of $48,000. She logs two payments, $12,000 and $8,000.

  • Amount Paid: $20,000
  • Amount Owed: $28,000

Her contractor finds rotted subfloor, and she approves a $3,500 change order.

  • Base Budget: $48,000
  • + $3,500 approved change orders
  • Total Budget: $51,500
  • Amount Owed: $51,500 minus $20,000, which is $31,500

Her base budget never changed. If she rejected the change order instead, every number would stay as it was.

  • Removing a line item deletes its cost estimate and the payments logged against it, and the total budget drops with it.
  • Amount Owed and the progress bar measure against the total budget, not the base. The moment you approve a change order, the amount left to pay rises.
  • In Detailed mode, the Estimated Budget card on the Budget tab adds up line items only. The Total Budget card at the top of the project includes approved change orders.
  • Approving a change order that adds days to the schedule also moves the project’s target completion date back by those days, when the project has one.
  • The budget a deal carried while you analyzed it is separate from the project’s budget. After the project exists, change its budget on the project’s Budget tab.